Project Experience
Installation - Projects
1) CMI-Thai Services Co., Ltd (IRPC Plant /Thai MAA) (March, 2009 to February, 2010)
▪ HRSG & Heat Exchanger Maintenance work ▪ Boiler Tubes Replacement
2) RMS Quality Co., Ltd (ABP3 Combined Cycle Cogeneration Plant Amata Nakorn Chonburi) (January, 2011 to June, 2012)
▪ BOP – Pipe & Supports installation volume 7,684 DB
3) Maintech Group (ABP3 Combined Cycle Cogeneration Plant Amata Nakon Chonburi) (December, 2011 to May, 2012)
▪ Demonetized, CT-Make up, and Service water storage tank installations / OD 12,500 mm, High 15,527 mm
4) RMS Quality Co., Ltd (ABPR1&2 Combined Cycle Cogeneration Plant Amata City Rayong) (October, 2012 to March, 2013)
▪ BOP – Pipe & Supports installation volume 8,206 DB
5) RMS Quality Co., Ltd (ABP4&5 Combined Cycle Cogeneration Plant Amata Nakorn Chonburi) (October, 2014 to October, 2015)
▪ BOP – Pipe & Supports installation volume 20,586 DB
6) RMS Quality Co., Ltd (BWCE Combined Cycle Cogeneration Plant Hemaraj Chonburi) (November, 2015 to April, 2016)
▪ BOP – Pipe & Supports installation volume 14,703 DB
7) RMS Quality Co., Ltd (BPU Ban Pong Utilities SPP) (May, 2016 to Mar, 2017)
▪ BOP – Pipe & Supports installation volume 14,609 DB
8) RMS Quality Co., Ltd (ABPR3&4 Combined Cycle Cogeneration Plant Amata City Rayong) (April, 2017 to February, 2018)
▪ BOP – Pipe & Supports installation volume 20,958 DB
9) RMS Quality Co., Ltd (ABPR5 Combined Cycle Cogeneration Plant Amata City Rayong) (February, 2018 to August, 2018)
▪ BOP – Pipe & Supports installation volume 11,503 DB
10) RMS Quality Co., Ltd (BPRP1 Combined Cycle Units 1-2 Replacement) Project (October, 2019 to September, 2020)
▪ BOP – Pipe & Supports installation volume 42,623 DB
11) RMS Quality Co., Ltd (BPLC1R Combined Cycle Cogeneration Plant Laem Chabang) (December, 2020 to February, 2021)
▪ STEAM TURBINE – Internal Pipe & Supports installation volume 1,321 DB
12) RMS Quality Co., Ltd (ABP1R2R Combined Cycle Cogeneration Plant Amata Nakorn Chonburi) (November, 2021 to October 2022)
▪ BOP – Pipe & Supports installation volume 37,519 DB
13) RMS Quality Co., Ltd (BPAT23 Combined Cycle Cogeneration Plant Project) (Angthong Power Plant) (November, 2022 to September, 2023)
▪ BOP – Pipe & Supports installation volume 27,641 DB
Fabrication - Projects
1) BJC Heavy Industries Public Co., Ltd (Santos Project Phase 1st to 5th)
▪ Fabrication • Platform and structure 1662 skids (2,242.7 ton)
• Piping 598 skids • 415 Pressure Vessels (523.9 ton)
▪ Pressure Testing
• 29,871 Spools • 350 Vessels Volume of work :(Piping: 248,513 DB) (Platform, Structure and Vessels 2766.6 ton)
-
CT Make-up Water TankAmata B. Grimm Power Plant 3
-
Storage Tank FabricationSteel Craft Co., Ltd.( Rayong )
-
ABP4&5Amata B. Grimm Power Plant 4&5
-
BPUBan Pong Utilities SPP Project
-
ABPR3&4Amata B. Grimm Power City Rayong 3&4
-
ABPR5Amata B. Grimm Power City Rayong 5
-
ABP1R2RAmata B. Grimm Power Plant 1&2Replacement
-
BPAT23B.Grimm Power (Angthong) 2&3